NEWS

CURRENT PROJECT UPDATES

11 E. LENOX

Final
Site prep: Done, Foundation: In Progress
  • Project Type
  • Completion Date
  • Current Status

TL:DR - Multifamily / Passive / CLT

This project is an innovative 7-story, mixed-use, multifamily building with a unique structure that required no podium. It will be constructed with CLT/Mass Timber for greater safety, efficiency, and a reduced carbon footprint. It will include a host of energy efficient features and is designed to meet Passive House standards.

September 1, 2022

Mass Timber construction has begun! The 1st floor is well underway.

1005 BROADWAY

Final
Site prep: Done, Foundation: In Progress
  • Project Type
  • Completion Date
  • Current Status

TL:DR - Multifamily / Passive 

This project will be an affordable 38-unit multifamily development in Chelsea that will restore a long-vacant and blighted parcel. It has been designed and will be built to Passive House standards. Among other energy-saving features, it will have an all-electric HVAC system and rooftop solar panels.

September 1, 2022

Steel beams are being erected

59-63 WILLOW

59 Willow
Final
Foundation: Done, Framing: In Progress
  • Project Type
  • Completion Date
  • Current Status

TL:DR - Multifamily / Passive 

This project will be a 3-story, 18-unit mixed income, and mixed use building located in the heart of Hamilton’s downtown. It has been designed and is being built to Passive House standards. This project represents a long-time vision of the town to add sorely needed, well-located, well-designed affordable housing to their community.

July 1, 2022

Framing is finished and we're currently beginning to install the SIGA weather wrapping

3171 WASHINGTON

Final
Site prep: In Progress
  • Project Type
  • Completion Date
  • Current Status

TL:DR - Multifamily / High-Performance

This will be a mixed-use multifamily development with 9 condo units and 1 commercial space located in the Egleston Square neighborhood.

June 1, 2022

Sitework underway

5-9 TOVAR (COMING SOON)

screencapture-us02-procore-com-562949953524472-project-drawing_areas-562949953488936-drawing_log-view_fullscreen-562949959938788-1632774200721
Final
Construction: Pending
  • Project Type
  • Completion Date
  • Current Status

TL:DR - Multifamily / High-Performance 

More information about this project will be coming soon. Please stay tuned!

TBD

Preconstruction

PROJECT SPOTLIGHTS

Click through the points on the map below to watch our project spotlight videos!

LATEST BLOG POSTS

Scroll through the posts below to see what we've been up to!

#DitchThePodium: Why Mass Timber is Optimal for Green Building.  Read More

Utile x Haycon: Triple Decker Design ChallengeRead More

FOLLOW US FOR MORE NEWS & UPDATES